Current Projects

Recent Projects

9 Structures Elevation Project for the Gwichyaa Zhee Gwich’in Tribe, Ft. Yukon

To protect critical community infrastructure in Fort Yukon from increasing flood risks, Drennon Construction completed a design-build project to elevate nine essential structures above the FEMA-designated 100-year floodplain. The project included raising seven residential homes, a preschool facility, and the Fort Yukon Tribal Hall—structures ranging from 600 to over 5,400 square feet—an average of 4.4 […]

Kotlik Home Relocation and Access Boardwalk Project

In May 2025 Drennon Construction successfully completed the Kotlik Home Relocation and Access Boardwalk Project, which involved the relocation of up to twenty threatened homes to the elevated Kotlik Gravel Land Subdivision (Plat 2013-1), located on the former community runway. The runway site, measuring approximately 35 feet wide by 2,200 feet long and elevated 5.5 […]

City of Valdez, Meals Hill Park Development Phase 1

Successfully completed the Meals Hill Park Access and Trail Development Project in June 2025 as the prime contractor. The project included the construction of the main public access area, complete with parking, a drop-off zone, and an entry plaza that serves as the primary gateway to Meals Hill Park. In addition, the team constructed approximately […]

Galena Flood Home Raising and Moving

In the spring of 2014 DCC was contracted to raise, move, and provide permanent helical piling’s, on some 41 homes flood damaged and below the newly established 100 year flood plain of 136.5 feet to sill. To date DCC has performed complete work on 31 of the 41 homes, and is scheduled to complete the remaining in the spring […]

2014 FEMA Galena Construction Support

In the spring of 2014 Drennon Construction was contracted by FEMA to help support the rebuilding efforts in Galena, Alaska. Working to support the volunteer efforts to build new homes where the Yukon river had swept the residence old homes away during the spring 2013 flooding, DCC cleared, grubbed, and installed new pads, driveways, and […]

Past Projects Archive

Coldfoot to Deadhorse Long Haul Fiber Project Segment 4 –MP 175‐242 of the Dalton Hwy ~69.9 Miles.

Successfully installed, and restored landscape to original condition on over 60 miles of 2 separate 1 ¼-inch fiber optic conduit HDPE conduits, and approximately 100 slack or splice hand hold boxes for a new back bone fiber line in remote areas of northern Alaska. The fourth segment of the system will later tie into both […]

Coldfoot to Deadhorse Long Haul Fiber Project Segment 3 MP 245‐300 of the Dalton Hwy ~51.7 Miles.

Successfully installed and restored landscape to original condition on over 40 miles of 2 separate 1 ¼-inch fiber optic conduit HDPE conduits, as well as approximately 75 slack or splice hand hold boxes for a new back bone fiber line in remote areas of northern Alaska. The third segment portion of the system is ongoing […]

DNR Richardson Highway Roadside Approaches

Bowers Investments Emergency Septic System Replacement

Tanana Lakes Wetlands Restoration Fairbanks, AK

Port Alexander Boardwalk Project

DNR Toilet Replacement Project Kenai and Fairbanks

Harding Lake SRA Expansion and Boat Ramp Replacement

Marx Creek Fish Spawning Channel Project- USDA

Tenderfoot Creek Campground Refurbishment

GCI Communication Parks Highway Fiber Project

Government Peaks Alpine Ski Trails Mat Su Borough

Alaganik Slough Boat Ramp Replacement Cordova, AK

 

UAF AG Farm Septic System Replacement Fairbanks, AK

In 2013 Drennon Construction was contracted to install a new septic system for the University of Alaska Fairbanks, this work consisted of constructing a new septic system serving the UAF Agricultural Farm, and a switchover from the existing and failing city utility system. The system was originally designed to be installed across from the farm buildings complex […]

Tangle Lakes Campground Refurbishment Paxson, AK

        

Tangle Lakes Access Road Improvements Paxton, AK

Drennon Construction